What is UHBVN (Uttar Haryana Bijli Vitran Nigam Limited)?

Before knowing how to apply UHBVN New connection, it is important to know that UHBVN is a power distribution undertaking owned by Haryana State Government, also known as Uttar Haryana Bijli Vitran Nigam Limited. It supplies electricity to the northern parts of the state of Haryana. Its headquarters is located in Panchkula, Haryana, adjoining Chandigarh. The Chief Minister of Haryana heads this company.

Presently Panchkula and Rohtak are the two operation zones of this company. A Chief Engineer heads each zone. There are five circles in each zone. Panchkula zone comprises Ambala, Yamunanagar, Kurukshetra, Karnal, Kaithal, and Rohtak zones with Panipat, Sonipat, Jind, Rohtak, and Jhajjar. A Superintending Engineer heads each circle.

Presently this company supplies electricity to about 60 cities in the above-mentioned 10 districts of Northern Haryana. The company provides electricity to about 31 lakh consumers in the industrial, agricultural, non-domestic and domestic sectors of Northern Haryana.

How to Apply UHBVN New Connection Online

You live or do business in Ambala, Yamunanagar, Kurukshetra, Karnal, Kaithal, Panipat, Sonipat, Jind, Rohtak, and Jhajjar in Haryana. If you want to get a domestic or commercial electricity connection there, you must apply in Panchkula and Rohtak zone under Uttar Haryana Bijli Vitran Nigam Limited.

UHBVN New Connection Process:

For UHBVN New Connection, some steps have to be taken by the consumer, and some steps for SDO.

Steps for Consumers

 Step-1: For UHBVN New E-connection, first go to the official website of the Haryana Government  Some instructions will be found on the web portal’s main page, first read them thoroughly.

Step 2: To apply the UHBVN New Connection, click on the Apply button in the Consumer Log in the Home Page section.

UHBVN New Connection Application Form –

Step 3: As you click on Apply. The Online Application form for UHBVN New Connection will open on your screen. Fill in the General Information like Circle, Sub Division, Category, Date, Application for, Type of Supply from the Application Form’s Dropdown list.

Step 4: After this, fill in all the information sought, including your name and address in the Applicant Particulars Details section.

Step 5: In the Applied Load Details section, fill the information about Consumer Connected Load, Purpose of Supply, Contract Demand & Supply Metering Equipment, etc.

Required Documents for Apply Online UHBVN New Connection

Step 6: You must have some papers for the UHBVN New Connection. Such as:

  • User Photo (File size less than 500KB).
  • Proof of Identity (File size less than 500KB).
  • Proof of Ownership (File size less than 500KB), all these documents Upload according to the defined file size.

Step 7: If you have already taken any Connection and want to get other UHBVN new connection in the same Premise / Property. So fill in the information about Account Holder, Account Number, Address, Category, Connected Load (KW), and Contract Demand (KVA) given in the application form.

Step 8: After filling the form, check the box of terms and conditions given below and fill the captcha. After this, click on Apply Button.

Step 9: A popup message of Final Save and Payment will appear on your screen. The application number will also be given with the message, “Your application has been successful.” Here, a link to Print out the Application Form will also be found. Go to this link and take a print out of the application form.

Step 10:

  • Carefully check Print Out whether all information is correct or not.
  • If you want to edit something, click on the button “No, I want to edit.”
  • After editing, click on Button Yes Submit given below.

UHBVN New Connection Payment

Step 11: UHBVN New Connection Consumers should keep in mind that within seven days of submitting the Online Application Form for New Connection, they must make Charge Payment within seven days, else their application will be canceled by the Department. This payment can be made both online or offline. After payment, UHBVN must get New Connection Payment Receipt.

Step 12: If you want to make an offline payment, then (i) Nigam Counters (ii) Epay Inforserve Pvt. Ltd, Panipat (iii) Atal Seva Kendra / Common Service Center (CSC) (iv) Harco Bank etc. The platform can be paid online.

Step 13: If you want to make an online payment, then (i) NEFT / RTGS (Yes Bank) (ii) Point of Sale (Yes Bank) (iii) Paytm (One 97 Communications) (iv) Via Bill Desk (Net Banking ) (v) UHBVN mobile app (vi) Payment can be made through a platform like Google Pay / PhonePe.

Step 14: For online, you have to fill your application number in the Enter E Form Number Column by going to the “Pay Charges Online” section of the official website and submitting it can make an online payment.

Step for Sub Divisions: –

The SDO starts its work after the consumer submits the application form and submits the UHBVN New Connection payment. For which he follows the following steps –

Step 1: The SDO will log in to the official website and checks the applicant’s online application and the papers uploaded with it, along with the online/offline payment. If all the documents are correct, they will allow them. If the documents are not right, they can cancel it.

Step 2: If the SDO understands that it is necessary to Verify the New Connection site, it will Verify it. If Payment Offline is done, then SDO receipt no. Fill in the form.

Step 3: SDO will approve Load with Allotted Feeder & Transformer Details.

Step 4: After this, the SDO will issue a Demand Notice to the consumer along with the estimated amount. When the Demand Notice is issued, the department sends an Alert through email to the consumer to deposit the Demand Notice amount. The consumer can deposit this amount either offline or online.

Step 5: SDO will complain of Demand Notice and Test Report.

Step 6: After the fieldwork is over, the SDO can issue the SCO if needed.

Step 7: If your load is more than 50KW, SDO conducts CEI Inspection, and after that, it releases a new Connection to the consumer.

UHBVN New Connection Applicaton Charges

  • If you want to see the Charge on Connection before taking UHBVN New Connection, then for this, you should go to the official website of the Haryana Government.
  • Go to Calculate Your Charges in the Dashboard and fill in Category, Load & Meter Equipment information there.
  • As you fill in this information, Application Processing Charges & Demand Notice Charges will be displayed on the screen.
  • If you want to see Detail, then click on the “View Detail” button below.
  • You will get details of Application Processing Fee, Advance Consumption deposit charges, Meter Installation Charges, Meter Testing Charges & Fixed Service Connection Charges along with all types of Charges.

Track UHBVN New E-connection Status

  • If you have submitted the online application for UHBVN New Connection and want to track it, you should visit the official website of the Haryana Government https://econnection.uhbvn.org.in/.
  • Go to the section of “Track the Status or Pay Charges Online” in the Dashboard, fill your application number in the Enter E Form Number column, and click on the “Track” button. The status of your UHBVN online connection status will come on your screen.

New E-Connection UHBVN Helpline Number

For No Supply Dial Toll-Free –

Phone No .: 1912 Or 1800-180-1550

Email ID: 1912@uhbvn.org.in 

Whatsapp No. : 9815961912

For New Connection: 1800-180-1550

Email ID: NewConnection@uhbvn.org.in

Website: https://econnection.uhbvn.org.in/  

If anyone is having trouble getting UHBVN New E-connection, they can mail it to the Electricity Department at NewConnection@uhbvn.org.in. The department will resolve its problems.

UHBVN Related FAQs: –

Q-1. What is Energy Meter?

Ans: Energy Meter is a type of device used to measure the electricity spent by a consumer.

Q-2. What does Fast Meter mean?

Ans: Generally, when one meter records more energy than another meter, it is called a fast meter. This comparison is quite confusing. As stated earlier, only meters with positive accuracy errors should be called fast meters.

Q-3. What does MDI mean to the consumer?

Ans: The full name of MDI is Maximum Demand Indicator. It is an indicator of the maximum power consumption consumed by the consumer for over half an hour. This parameter is essential for both the consumer and the service company to decide the allowable load and plan the network capacity. If the weight of your Connection is more than the sanctioned load, you can be fined.

 Q-4. What does MRI Reading mean?

Ans: Its full name is the Meter Reading Instrument. It is a gadget used to download data. It records data better without any human error.

Q-5. What is an AMR System?

Ans: Automatic Meter Reading is the full name of AMR. It is also called an automatic meter reading (AMR) system. The device automatically reads the meter’s consumption without manual intervention and sends it to the company’s server.

Also Read: –

 

Guru R.P.: I am a part-time blogger, Hindi Abhimaan is a platform where people are informed about various schemes launched by the Government of India and various state governments as well as various services being run to make the benefits of these schemes accessible to the general public so that People can have easy access to these services.